单项选择题
Hatch No.1 must be cleaned up to meet the()of the cargo surveyors.
A.necessity
B.responsibility
C.requirement
D.stipulation
点击查看答案&解析
相关考题
-
单项选择题
During fueling,all doors,hatches,and ports().
A.to windward should be opened and the ones to leeward should be closed
B.to leeward should be opened and the ones to windward should be closed
C.should be opened
D.should be closed -
单项选择题
Cracks may be prevented from developing at the corners of welded plating inserts by().
A.squaring the corners
B.rounding the corners
C.plug welding the corners
D.slot welding the corners -
单项选择题
Connecting elements of a mooring system should be fabricated from().
A.cast iron
B.forged steel
C.stainless steel
D.cast steel