欢迎来到易学考试网 易学考试官网
全部科目 > 计算机软件水平考试 > 高级系统架构师 > 信息系统综合知识 > 专业英语

单项选择题

()is the process of obtaining the stakeholders’ formal acceptance of the completed project scope.Verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.

    A.Project acceptance
    B.Scope verification
    C.Scope definition
    D.WBS Creation

点击查看答案&解析

相关考题

微信小程序免费搜题
微信扫一扫,加关注免费搜题

微信扫一扫,加关注免费搜题