In the process of communication requirement analysis, the project manager should consider the number of potential communication channels or paths as an indicator of the complexity of a project’s communication. According to Metcalfe’s Law, a project with 10 stakeholders has () potential communication channels.
A、10
B、45
C、50
D、100
点击查看答案&解析
相关考题
-
单项选择题
A () is a collection of projects and other work that are grouped together to facilitate effect -ive management of thatwork to meet strategic business objectives.
A、program
B、portfolio
C、project of large size
D、PMO -
单项选择题
Quality planning tools are often used to help plan effective quality management activities.() is one of such tools,which involves company actual or planned project practices to those or other projects to generate ideas for improvementand to provide a basis by which to measure performance.
A、Benchmarking
B、Quality metric
C、Quality checklist
D、Brainstorming -