单项选择题
Refer to the exhibit. ROUTE.com is planning to implement a secure OSPF network to support traffic between clients on the 172.16.10.0/24 network and the file server on the 172.16.20./24 network. You have been asked to review the implementation and verification plans for this OSPF project. Which statement about the plan is true? ()
A. It is complete as written
B. It should include a task that verifie s that the interarea routes are using the proper MED
C. It should include a task that verifies that load sharing is active on R1 and R4
D. It should include a task that verifies that all redundant links will become active when the primary links are sh ut down
相关考题
-
单项选择题
Refer to the exhibit. ROUTE.com is planning to implement a secure OSPF network to support traffic between clients on the 172.16.10.0/24 network and the file server on the 172.16.20./24 network. You have been asked to review the implementation and verification plans. Which statement about the plan is true?()
A. It is complete as written
B. It should include a task that verifies that the interarea routes are using the proper MED
C. The plan should include a task that verifies that load sharing is active on the appropriate links
D. The plan should include a task that verifies end - to - end connectivity between the clients and the file server -
单项选择题
Refer to the exhibit. ROUTE.com is planning to implement a new secure OSPF network to support traffic between clients on the 172.16.10.0/24 network and the file server on th e 172.16.20./24 network. You have been asked to review the implementation plan for the OSPF project. Which statement about the plan is true?()
A. It is complete as written.
B. It should include a task that shuts down all unused interfaces.
C. It sho uld include tasks that enable and verify OSPF authentication.
D. It should include a task that establishes a file transfer baseline before and after the configuration is changed. -
单项选择题
Refer to the exhi bit. ROUTE.com is planning to implement load balancing for traffic between host on the 172.16.10.0/24 and 172.16.20./24 networks. You have been asked to review the implementation plan for this project. Which statement about the plan is true?()
A. It is complete as written.
B. It should include a task to configure multipath to equal a value of 2 on R1 and R4.
C. It should use a ping instead of a traceroute to validate that load balancing has been activated.
D. It should conta in a task that documents the changes made to the configurations.