单项选择题

Refer to the exhibit. ROUTE.com is planning to implement a secure OSPF network to support traffic between clients on the 172.16.10.0/24 network and the file server on the 172.16.20./24 network. You have been asked to review the implementation and verification plans for this OSPF project. Which statement about the plan is true? ()

    A. It is complete as written
    B. It should include a task that verifie s that the interarea routes are using the proper MED
    C. It should include a task that verifies that load sharing is active on R1 and R4
    D. It should include a task that verifies that all redundant links will become active when the primary links are sh ut down

点击查看答案